Kapalua Bridge Kapalua Adventure Course, Maui, HI Click on any image to go back to the Kapalua Bridge Specifications Page Construction Images, May-July 2008
|
||
Ken Gilman delivers a mainline spool over rough terrain.
|
Gabe Newton hauls the other three by truck.
|
|
South piles in the ground.
|
Excavators at north abutment.
|
|
Sunset from the bridge site.
|
North abutment: screwing in helical piles with torque motor.
|
|
Carroll Vogel hanging out on the edge.
|
Aaron Nelson with geo-technical inspector Rick Cooper; starting a pile.
|
|
Robert Mitton and Steve Howell cut the pile tops to design elevation.
|
Helical pile after installation at 10,000 ft pounds.
|
|
Ken and Steve assemble the first tower leg.
|
Robert and Steve assemble number two.
|
|
Robert and Steve show their work: Two complete north tower legs.
|
Robert and Carroll tag team the south anchor excavation.
|
|
View down in the hole from big excavator.
|
Carroll and Robert form a bucket brigade on north side.
|
|
Robert checks the anchor face angle as Carroll adjusts it with the bucket.
|
Unorthodox crane: Test lift of a tower leg with the excavator (sans bucket).
|
|
Mary Pat Mitton moves forms to the north abutment.
|
North abutment: Aaron, Austin Thompson, Ken and Marty Walz tie rebar.
|
|
The Hawaiian Cement truck backs to the south abutment.
|
Austin and Aaron direct concrete into the north abutment.
|
|
Austin and Steve prep the mainlines for socketing.
|
Steve and Austin level the bridge bowl prior to pouring molten zinc.
|
|
Marty challenges Austin for spool dominance.
|
Aaron on tag line: Tries to pull it alone.
|
|
Austin and tower leg number one.
|
Ken and Gabe affix a tower leg to the excavator for lifting into position.
|
|
The tower raisers.
|
Gabe packs some dirt over the anchors.
|
|
The excavator is dwarfed by the 52' tower.
|
Ken hustles to get the tower base bolts snug.
|
|
Ken up on the tower.
|
Tower leg two goes up at the south abutment.
|
|
Steve and Ken assemble the tower horizontals.
|
Austin strikes a pose during north tower top horizontal assembly.
|
|
Tower leg three goes up, north abutment.
|
Marty releases the tower leg from the excavator.
|
|
Compacting and testing of soil density at the south anchorage.
|
Carroll during work at the north tower top horizontal.
|
|
Marty on the completed tower.
|
View of the job site from north tower top.
|
|
Aaron with geo-tech Rick Cooper.
|
Patrick O'Donnell and Steve ready the first mainline for pulling.
|
|
Steve and Patrick at tower top during mainline pull.
|
Three mainlines are across.
|
|
Carroll stands on mainlines, more than 200 feet up.
|
A double rainbow graces the bridge.
|
|
Bosun Chair work: Carroll installs the first suspender.
|
Austin and Ken enjoy the view from north abutment.
|
|
Austin in the bosun's chair, installing suspender assemblies to the paired mainlines.
|
||
Out over Kaopala Gulch; Austin in the distance installing suspenders.
|
Six suspender pairs installed, 30 to go.
|
|
Gabe's turn in the bosun's chair; installing floor beam/suspender assemblies.
|
Carroll and Aaron assess the next step during skyline set up.
|
|
Aaron and Carroll hauling stringer assemblies to Ken; tying the hanging floorbeams together.
|
||
Lattice tower and the nature preserve above the bridge site.
|
A sunset from the tower top.
|
|
Bridge enthusiast and photographer Patrick.
|
Chief engineer Al "Mike" Highberger, PE.
|
|
Nearly finished.
|
View through decking from below.
|
|
Kapalua Bridge on completion day: 7/14/08.
|